How Long Does a Bathroom Remodel Take?
Quick answer.
Most bathroom remodels take 3 to 8 weeks, according to HomeGuide: 3 to 4 weeks for simpler projects and 6 to 12 weeks or more for large ones. Sweeten's general contractors put construction at 20 to 30 working days and the whole project, from planning to punch list, at six weeks to three months.
Timeline by phase
| Phase | Typical duration |
|---|---|
| Site visits and bids | 1–3 weeks |
| Compare bids, choose a contractor | 1–2 weeks |
| Sign contract, set schedule | 1 week |
| Permits and approvals | As little as 2 weeks; a couple of months is more common |
| Demolition | 1 day |
| Reroute plumbing and electrical | 1–2 days |
| Inspection | About 1 hour on site; scheduling can take days or weeks |
| Floor tile | ½–1 day |
| Tub, vanity, sink, toilet, tiling, lighting | 1–3 days |
| Punch list | 1–5 days |
What causes delays
Sweeten names city permits and board approvals as the most common causes of delay, and notes that materials with long lead times also hold projects up. Order tile, fixtures and vanities as soon as the design is final.
Budget time and money for surprises: see bathroom remodel costs.
Ask contractors for a written schedule
Compare quotes and timelines from local bathroom remodelers through MyHomeQuote.
Operated by MyHomeQuote.
Sources
- HomeGuide, Bathroom Remodel Cost. homeguide.com
- Sweeten, Bathroom Renovation Guide: Permits, Contractors & Detailed Timeline. sweeten.com